AI Data Centre · Level 5 of 8

PUE from a month of meters

Level 5 of 8 in the AI Data Centre: a free data centre exercise at Intermediate level. Work out the hall's power usage effectiveness from 30 days of meter readings, then decide which of five upgrades saves the most energy.

Start this level

Free · no download. Your work is saved on this device. Updated 18 Oct 2026.

3D view of the PUE from a month of meters level in the AI Data Centre
PUE from a month of meters

The brief

Client
Meadowbank Analytics
Site
Main hall, Hillcrest campus
Work order
WO-DC-105
Task code
DC-05
Difficulty
Intermediate
Type of work
Reporting

Work out the hall's power usage effectiveness from 30 days of meter readings, then decide which of five upgrades saves the most energy.

Skills you practise

  • PUE
  • Reading energy meters
  • Where the overhead goes

What the test checks

The acceptance test marks the skills this level practises.

  • PUE
  • Reading energy meters
  • Where the overhead goes

In this lab

  • Rack and cable GPU servers
  • Power budgets and cooling
  • GPU jobs and a DCIM view

Levels in the AI Data Centre

Previous: Cooling hot spotNext: Replace a failed part from a ticket

  1. Safety walk and hall tour
  2. Rack and cable a GPU server
  3. Rack power budget
  4. Cooling hot spot
  5. PUE from a month of meters
  6. Replace a failed part from a ticket
  7. Training job slowdown
  8. Power event drill

Part of the AI Data Centre

Walk an AI data hall, rack and cable a GPU server, and size its power and cooling.

About the AI Data Centre

Feeds these internships: AI and Machine Learning, Data Science and Analytics, AI Agents and Automation, Electrical Design.